PWSA Street Restoration Updates
Posted on: March 22, 2024 - 1:27pm
Some updates concerning street restoration work being done by PWSA:
- Crews will begin milling and adding binder-to-grade on the following streets Monday: Clara, Van Buren, Seigel, Beckert
- Milling and binder should be complete by end of week. They will then continue with paving sometime the next week. In this intermediary phase, the road will be drivable.
- Milling/binder should take 1-2 days per block of work.
- Crews are posting no parking signs today and Monday for this work.